COMPANY'S HISTORY

History

MunaiTas North-West Pipeline Company Limited Liability Partnership (abbreviated name of the company — MunaiTas NWPC LLP) was created on December 11, 2001 in order to realize construction and operation project of the Kenkiyak-Atyrau oil pipeline. Company shareholders are:

  • KazTransOil JSC, owning 51% Company shares;
  • CNPC Exploration and Development Company Ltd., owning 49% Company shares.

Main activity of the Company is oil transportation services through main oil pipeline.

2001 December

On December 11, 2001, MunaiTas NWPC LLP was established in order to implement the project for the construction and operation of the Kenkiyak-Atyrau oil pipeline.

2004 January

Since January 2004, MunaiTas NWPC LLP has been included in the State Register of Natural Monopoly Entities of the Republic of Kazakhstan.

2004 June

On June 18, 2004, by Order No. 135 of the Minister of Energy and Mineral Resources of the Republic of Kazakhstan, the Act of the State Acceptance Commission was approved on the acceptance of the constructed facility: “Kenkiyak-Atyrau Main Oil Pipeline into Operation”, with the cost of fixed assets put into operation 31 billion tenge. 

2005 May

On May 16, 2005 MunaiTas NWPC CJSC was re-registered as NWTK MunaiTas JSC, in accordance with paragraph 1 of Article 90 of the Law of the Republic of Kazakhstan “On Joint Stock Companies” and the change of location (state registration number 44641-1910-AO) .

2011 Novermber

In 2011, it was approved by the Order of AREM dated November 7, 2011. No. 351-OD specific tariff in the amount of 5,912 tenge per 1 ton per 1,000 km for the entry period from January 1, 2012.

2012 January

January 19, 2012 was approved by the AREM Order No. 8-OD on amendments to the AREM Order dated November 7, 2011. No. 351-OD, a new specific tariff in the amount of 5,912 tenge per 1 ton per 1,000 km came into effect on April 1, 2012.

2016 April

On April 14, 2016, the KREM Order was approved jointly with the order of the Ministry of Energy of the Republic of Kazakhstan dated April 29, 2016, the Investment Program of the Partnership for 2016-2020 was approved.

2018 June

On July 24, 2018, MunaiTas NWPC JSC was reorganized by reorganizing it into North-Western Pipeline Company MunaiTas LLP (hereinafter referred to as MunaiTas LLP, the Partnership).

2020 June

On June 15, 2020, an act of acceptance of objects into operation for the 1st launch complex was signed.

2021 June

On June 30, 2021, an act was signed for the acceptance of facilities for operation at the 2nd launch complex (technological facilities of PS Aman);

2021 June

On June 30, 2021, an act of acceptance of facilities for operation of the preheating furnace facility was signed.

2021 July

Since July 1, 2021, the possibility of pumping oil in the reverse direction through the technological facilities of PS Aman has been provided. All equipment is operating normally.

2021 November

By order of the DCRM dated November 26, 2021 No. No. 132-OD, the tariff estimate was approved, taking into account changes for 2021.